Risen Energy’s Merredin Solar Farm is powering on

Risen Energy’s 132 MWdc Merredin Solar Farm has completed all pre-commissioning testing on major plant and equipment and is now in the stages of starting the commissioning process. Western Power and Merredin Solar Farm are doing functionality checks and getting ready for the first back energisation to start the live commissioning process.

After all functions are checked and confirmed, Merredin Solar Farm will start exporting into the grid in four stages – Stage 1 will be at 20% capacity, Stage 2 will be at 50% capacity, Stage 3 will be at 80% capacity and Stage 4 at 100% capacity. This will happen over a pre-determined time as controlled by the Network Service Provider, Western Power.

On site, staff and contractors are undergoing rectification and adjustment works according to discoveries made during the QA process. The operations building has been installed on site and Risen are demobilising the temporary construction site offices and amenities.

Re-planning the resources and tasks to be completed on all work on site is being conducted within the current work guidelines to ensure a safe and healthy work environment for all involved. Due to the COVID-19 situation, Risen has adapted their operations and business. They have taken extra care to ensure a safe and healthy work environment for their employees and external stakeholders.

Scroll to Top