Woodland BESS
250 MW / 1,000–3,000 MWh
Approved — grid connection in progress
A 250 MW battery in the Riverina, designed to deliver four to twelve hours of storage so the configuration can be matched to the offtake or tolling structure that is ultimately contracted. It is the largest storage project in Risen’s Australian pipeline. Land and development approval are secured; the generator performance standard package for grid connection is now being prepared.
- Location
- Darlington Point — Riverina, New South Wales
- Storage duration
- 4 to 12 hours, configurable to the offtake
- Land secured — complete
- Development approval — complete
- Grid connection — in progress
- Construction — upcoming