Development

Development pipeline.

Four utility-scale battery and solar projects across South Australia, New South Wales and Queensland — approved, grid-ready or nearly there — open for expressions of interest from investors, co-developers and acquirers.

  • 4 Projects open for interest
  • 700 MW Battery power
  • 1.95 GWh Battery energy
  • 250 MW Co-located solar
  • 3 States (SA, NSW, QLD)
Artist’s impression of the Bungama West battery energy storage project in South Australia
Artist’s impression — Bungama West BESS, South Australia.

Investment opportunities

Projects open for interest.

SA

BESS

Bungama West BESS

200 MW / 400 MWh

Construction-ready

A 200 MW / 400 MWh standalone battery beside the Bungama substation, one of the most advanced large-scale BESS sites in South Australia. Development approval and AEMO’s Section 5.3.4A clearance are in hand, and the project is ready to proceed to connection agreement and construction.

Location
Bungama, near Port Pirie — Mid North, South Australia
Grid connection
275 kV Bungama substation (ElectraNet)
Storage duration
2-hour
  1. Land secured — complete
  2. Development approval — complete
  3. Grid connection (5.3.4A clearance) — complete
  4. Construction — upcoming

NSW

BESS

Woodland BESS

250 MW / 1,000–2,000 MWh

Approved — grid connection in progress

A 250 MW battery in the Riverina with a storage duration of four to eight hours still to be decided — the largest storage project in Risen’s Australian pipeline. Land and development approval are secured; the generator performance standard package for connection to the Darlington Point substation is now being prepared.

Location
Darlington Point — Riverina, New South Wales
Grid connection
Darlington Point substation (Transgrid), 330 kV
Storage duration
4–8 hours (to be decided)
  1. Land secured — complete
  2. Development approval — complete
  3. Grid connection — in progress
  4. Construction — upcoming

SA

Solar + BESS hybrid

Geranium Plains

150 MW / 300 MWh + 250 MW solar

Approved — grid connection in progress

A co-located solar farm and battery on a single approved site in South Australia’s Mid North, with room to expand both the solar and storage capacity. The hybrid connects through a new substation on the 275 kV Para–Robertstown transmission line.

Location
Geranium Plains — Goyder region, Mid North, South Australia
Grid connection
New substation cutting into the 275 kV Para–Robertstown line (ElectraNet)
  1. Land secured — complete
  2. Development approval — complete
  3. Grid connection — in progress
  4. Construction — upcoming

QLD

BESS retrofit

Yarranlea BESS retrofit

100 MW / 250 MWh

Planning amendment lodged

A 250 MWh battery added to Risen’s operating 121 MW DC Yarranlea Solar Farm, sharing its site, lease and 132 kV grid connection. A planning amendment for the battery has been lodged and the connection package is ready for submission.

Location
Yarranlea — Darling Downs, Queensland
Grid connection
132 kV connection at the operating Yarranlea Solar Farm
Storage duration
2.5-hour
  1. Land secured — complete
  2. Development approval — in progress
  3. Grid connection — in progress
  4. Construction — upcoming

Complete In progress Upcoming

How a project gets built

Four stages from paddock to grid.

  1. 01

    Land secured

    Long-term lease or purchase rights over the site, with environmental and cultural-heritage assessments complete.

  2. 02

    Development approval

    State planning approval for the project as designed — the permit to build, subject to conditions.

  3. 03

    Grid connection

    Generator performance standards agreed with the network and AEMO, culminating in the Section 5.3.4A letter and an offer to connect.

  4. 04

    Construction

    Connection agreement executed, equipment procured and works under way through to commissioning and registration.

What’s on offer

Ways to get involved.

Each project can be taken on outright, developed jointly, or backed as an investment. Risen’s Australian team stays on to see it through.

  • Acquisition

    Take the project on as a de-risked, approved development and carry it through construction to operation.

  • Co-development

    Partner with Risen’s Australian development team through connection, procurement and delivery.

  • Investment

    Fund development or construction alongside a developer that has built and operated 100 MW+ solar farms in Australia.

  • Supply-backed

    Risen can supply the modules and battery systems, with local warranty and support — the same equipment behind its operating Australian assets.

Start a conversation.

Tell us which opportunity you’re interested in and our Australian development team will respond directly.